City of Temecula header
File #: AR-24-436    Version: 1 Name:
Type: Council - Consent Calendar Status: Agenda Ready
File created: 8/26/2024 In control: City Council
On agenda: 9/10/2024 Final action:
Title: Award Construction Contract to BWW & Company, Inc. for the Sidewalks - Citywide, Ynez Road (Rancho Highland Drive to Tierra Vista Road), PW17-28
Attachments: 1. Agenda Report, 2. Contract, 3. Project Description, 4. Project Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Award Construction Contract to BWW & Company, Inc. for the Sidewalks - Citywide, Ynez Road (Rancho Highland Drive to Tierra Vista Road), PW17-28

recommendation

That the City Council:

 

1. Award a construction contract to BWW & Company, Inc. in the amount of $279,813 for the Sidewalks - Citywide, Ynez Road (Rancho Highland Drive to Tierra Vista Road); and

 

2. Authorize the City Manager to approve change orders not to exceed the contingency amount of $83,944, which is equal to 30% of the contract amount; and

 

3. Approve a budget transfer of $77,393 in Measure S funds from the Sidewalks - Third Street Project, PW23-03 to the Sidewalks - Citywide, PWSW-02; and

 

4. Make a finding that the Sidewalks - Citywide, Ynez Road (Rancho Highland Drive to Tierra Vista Road), PW17-28 is exempt from Multiple Species Habitat Conservation Plan fees.