File #: AR-24-240    Version: 1 Name:
Type: Council - Consent Calendar Status: Agenda Ready
File created: 4/30/2024 In control: City Council
On agenda: 5/14/2024 Final action:
Title: Award Construction Contract to Beador Construction Company, Inc., for the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04
Attachments: 1. Agenda Report, 2. Contract, 3. Project Description, 4. Project Location, 5. Beador Letter (March 21, 2024), 6. City Letter to Leonida (April 2, 2024), 7. Leonida Email (April 2, 2024), 8. City Letter to Leonida (April 9, 2024)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Award Construction Contract to Beador Construction Company, Inc., for the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04

recommendation

That the City Council:

 

1. Approve the appropriation of $1,562,908 from DIF - Open Space & Trails to the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04; and

 

2. Reject the bid received from Leonida Builders, Inc. for the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04; and

 

3. Award a construction contract to Beador Construction Company, Inc. in the amount of $3,565,700 for the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04; and

 

4. Authorize the City Manager to approve construction contract change orders up to 10% of the contract amount, $356,570; and

 

5. Authorize payment of $9,831.95 to the Western Riverside County Regional Conservation Authority for the Multiple Species Habitat Conservation Plan fee required for construction of the Santa Gertrudis Creek Trail Phase II - Margarita Road Under-Crossing Project, PW19-04.