Award Construction Contract to Ace Capital Engineering for the Sixth Street Improvements, PW22-16
recommendation
That the City Council:
1. Approve the transfer of $120,000 of Measure S funds from the Sidewalks - Third Street Project, PW23-02 to the Sixth Street Improvements Project [Formerly, “Sidewalks - Old Town Improvements - South Side of Sixth Street (Old Town Front Street to Mercedes Street)”], PW22-16; and
2. Award a construction contract to Ace Capital Engineering in the amount of $665,523.17 for the Sixth Street Improvements [Formerly, “Sidewalks - Old Town Improvements - South Side of Sixth Street (Old Town Front Street to Mercedes Street)”], PW22-16; and
3. Authorize the City Manager to approve construction contract change orders not to exceed the contingency amount of $66,552.32, which is equal to 10% of the contract amount; and
4. Make a finding that the Sixth Street Improvements [Formerly, “Sidewalks - Old Town Improvements - South Side of Sixth Street (Old Town Front Street to Mercedes Street)], PW22-16 is exempt from Multiple Species Habitat Conservation Plan fees.